ALD have featured in the Stratford City newsletter InSite, this fifth issue focuses on the design aspects of the scheme and an introduction to some of the teams involved in the project.
ALD have commenced on site with the first areas of highway footpath finishes having been offered up for approval during August. The sub-base materials, movement joints, foundations and rebar elements within the pedestrian boulevard areas are also in progress. Procurement of natural stone has commenced. ALD are currently reviewing Contractor Submittals, responding to site queries and reviewing work in progress.